PJM-AG2-364
200 MW generation in Tazewell, IL · In queue since March 2021 · Proposed COD May 2024
200 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-31
PJM-AG2-364 is a proposed 200 MW solar generation project located in Tazewell County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 26, 2021. Its proposed commercial operation date is May 31, 2024.
The interconnection agreement for the project with utility ComEd is currently listed as "In Progress (unknown study)". The point of interconnection is the Powerton 345 kV substation. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
IL
County
Tazewell
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Powerton 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 3 POWERT24 KV PO-5
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.