Powerton 345 kV
200 MW generation in Tazewell, IL · In queue since March 2025
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Powerton 345 kV project is a 200 MW solar generation project located in Tazewell County, Illinois. It is in the PJM interconnection queue as project PJM-AG2-364, though it has been moved to the TC2 queue. The queue entry date is March 4, 2025.
The project is listed as active in the queue, and interconnects with ComEd. It is a Generation Interconnection project.
Generated from interconnection queue and public data sources
State
IL
County
Tazewell
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Powerton 345 kV