PJM-AG2-404
425 MW hybrid in Hardy, WV · In queue since March 2021 · Proposed COD June 2024
425 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
The proposed project PJM-AG2-404 is a 425 MW hybrid solar and battery energy storage development in Hardy County, West Virginia. Interconnecting to the Meadow Brook - Mt. Storm 500 kV II point of interconnection, the project consists of 425 MW of solar generation.
The project is in the PJM interconnection queue as of March 30, 2021, with a proposed commercial operation date of June 30, 2024. Its interconnection agreement status is listed as "In Progress (unknown study)". The utility is listed as APS.
Generated from interconnection queue and public data sources
State
WV
County
Hardy
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Meadow Brook - Mt. Storm 500 kV II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-404