PJM-AG2-405
10.98 MW generation in Putnam, OH · In queue since March 2021 · Proposed COD October 2022
10.98 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 7m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
PJM-AG2-405 is a proposed solar generation project with a total capacity of 10.98 MW. The project is located in Putnam County, Ohio, within the PJM Interconnection region. The interconnection request was entered into the PJM queue on March 30, 2021, with a proposed commercial operation date of October 31, 2022. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Continental 69 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Putnam
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Continental 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-405