PJM-AG2-411
63 MW generation in Somerset, PA · In queue since March 2021 · Proposed COD July 2024
63 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-01
PJM-AG2-411 is a proposed 63 MW solar generation project located in Somerset County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of March 31, 2021. The proposed commercial operation date is July 1, 2024.
The interconnection agreement for PJM-AG2-411 is currently listed as "In Progress (unknown study)". The point of interconnection is the Statler Hill 115 kV substation. The project is within the PENELEC utility territory.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Statler Hill 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- STATHILL34.5 KV FORWRDWF
- POI Substation
- Statler Hill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-411