PJM-AG2-418
40 MW hybrid in Perry, PA · In queue since March 2021 · Proposed COD May 2023
40 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 2m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-31
PJM-AG2-418 is a proposed 40 MW hybrid solar and battery project located in Perry County, Pennsylvania. The project consists of 40 MW of solar generation. It is in the PJM interconnection queue as of March 30, 2021, with a proposed commercial operation date of May 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility territory. It is interconnected at the Blain 115 kV point of interconnection. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Perry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Blain 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BLAIN 115 KV #1 TX
- POI Substation
- Blain Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-418