PJM-AG2-423
80 MW hybrid in Barbour, WV · In queue since March 2021 · Proposed COD June 2024
80 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
PJM-AG2-423 is a proposed 80 MW hybrid solar and battery project located in Barbour County, West Virginia. The project consists of 80 MW of solar generation, and is listed in the PJM interconnection queue, entered on March 30, 2021. The proposed commercial operation date is June 30, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is APS.
Generated from interconnection queue and public data sources
State
WV
County
Barbour
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Cherry Run_x0013_Harmony 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-423