PJM-AG2-426
59 MW hybrid in Sussex, VA · In queue since March 2021 · Proposed COD February 2024
59 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-29
PJM-AG2-426 is a proposed 59 MW hybrid solar and battery project located in Sussex County, Virginia. The project, which consists of 59 MW of solar capacity, is in the PJM interconnection queue as of March 30, 2021, with a proposed commercial operation date of February 29, 2024. The interconnecting utility is Dominion.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Wakefield - Waverly 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.