PJM-AG2-427
85 MW hybrid in Sussex, VA · In queue since March 2021 · Proposed COD February 2024
85 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-29
The proposed project PJM-AG2-427 is an 85 MW hybrid solar and battery energy storage development project located in Sussex County, Virginia. Interconnecting to the Dominion utility via the Waverly 115 kV point of interconnection, the project consists of 85 MW of solar generation.
The project is in the PJM interconnection queue with an entry date of March 30, 2021, and a proposed commercial operation date of February 29, 2024. Its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Waverly 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ESAYRE 34.5 KV SUNYSIDE
- POI Substation
- North Waverly Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-427