PJM-AG2-429
69 MW hybrid in Clarion, PA · In queue since March 2021 · Proposed COD February 2024
69 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-29
PJM-AG2-429 is a proposed hybrid solar and battery project located in Clarion County, Pennsylvania. The project, with a total capacity of 69 MW, consists of a 69 MW solar component. It is listed in the PJM interconnection queue as of March 30, 2021, with a proposed commercial operation date of February 29, 2024. The interconnection point is at the Burma - Armstrong 138 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The utility involved is APS, and the entity is PJM.
Generated from interconnection queue and public data sources
State
PA
County
Clarion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Burma - Armstrong 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-429