PJM-AG2-436
400 MW hybrid in Sussex, VA · In queue since March 2021 · Proposed COD December 2023
400 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG2-436 is a proposed 400 MW hybrid solar and battery project located in Sussex County, Virginia. The project, which consists of 400 MW of solar capacity, is in the PJM interconnection queue as of March 30, 2021. Dominion is the listed utility.
The proposed commercial operation date is December 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Carson - Rogers Road 500 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Carson - Rogers Road 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CARSON4 230 KV SR1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-436