PJM-AG2-444
346 MW generation in Pickaway, OH · In queue since March 2021 · Proposed COD December 2024
346 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AG2-444 is a proposed solar generation project with a total capacity of 346 MW, located in Pickaway County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 30, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement (IA) status for PJM-AG2-444 is currently "In Progress (unknown study)". The point of interconnection (POI) is the Bixby - Biers Run 345 kV line. The project is within the service territory of AEP. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OH
County
Pickaway
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Bixby - Biers Run 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-444