PJM-AG2-450
115.3 MW storage in Gloucester, NJ · In queue since March 2021 · Proposed COD March 2025
115.3 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
PJM-AG2-450 is a proposed 115.3 MW battery storage project located in Gloucester County, New Jersey. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 30, 2021. The proposed commercial operation date is March 1, 2025.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The designated point of interconnection is the Bridgeport 230 kV substation.
Generated from interconnection queue and public data sources
State
NJ
County
Gloucester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Bridgeport 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LINWDPE 18 KV CT1
- POI Substation
- Bridgeport Co Generation Substation