PJM-AG2-451
123 MW storage in Salem, NJ · In queue since March 2021 · Proposed COD June 2024
123 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
PJM-AG2-451 is a proposed 123 MW battery storage project located in Salem County, New Jersey. The project is interconnected within the PJM Interconnection queue, with an entry date of March 30, 2021. The proposed commercial operation date is June 1, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists solely of battery storage, with a total capacity of 123 MW. The interconnecting utility is AEC.
Generated from interconnection queue and public data sources
State
NJ
County
Salem
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Chambers 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CHAMBERS230 KV BUS3
- POI Substation
- Chambers Co Generation Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-451