PJM-AG2-457
80 MW generation in Mckean, PA · In queue since March 2021 · Proposed COD March 2024
80 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3 years
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-31
PJM-AG2-457 is a proposed solar generation project located in McKean County, Pennsylvania. The project, with a total capacity of 80 MW, is in the PJM interconnection queue as of March 30, 2021. The proposed commercial operation date is March 31, 2024.
The interconnection agreement for the project with PENELEC is currently in progress, with the specific study status unknown. The point of interconnection is at the Farmers Valley-Ridgeway 115 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Mckean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Farmers Valley-Ridgeway 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-457