PJM-AG2-460
2 MW storage in Hunterdon, NJ · In queue since March 2021 · Proposed COD August 2022
2 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 5m
Schedule
45 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-08-31
PJM-AG2-460 is a proposed 2 MW battery storage project located in Hunterdon County, New Jersey. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 30, 2021. The proposed commercial operation date is August 31, 2022. The interconnection agreement is currently listed as "In Progress (unknown study)". The designated utility is JCPL.
The development project consists solely of battery storage, with a total capacity of 2 MW. The point of interconnection is the East Flemington-Lebanon 34.5 kV II substation.
Generated from interconnection queue and public data sources
State
NJ
County
Hunterdon
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
East Flemington-Lebanon 34.5 kV II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.