PJM-AG2-466
1,000 MW hybrid in WV · In queue since March 2021 · Proposed COD June 2024
1,000 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
PJM-AG2-466 is a proposed 1000 MW hybrid solar and battery project located in West Virginia within the PJM Interconnection region. The project, which consists of 1000 MW of solar capacity, entered the PJM queue on March 30, 2021, with a proposed commercial operation date of June 30, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the Culloden - Wyoming 765 kV line.
The development project is classified as a hybrid due to its combination of solar and battery technologies. It is currently listed as an active project within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
WV
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Culloden - Wyoming 765 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CULLODEN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.