PJM-AG2-469
80 MW generation in Westmoreland, VA · In queue since March 2021 · Proposed COD December 2025
80 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AG2-469 is a proposed 80 MW solar generation project located in Westmoreland County, Virginia. The project is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of December 31, 2025. Dominion is the listed utility.
The interconnection agreement for PJM-AG2-469 is currently listed as "In Progress (unknown study)". The point of interconnection is the Westmoreland _x0013_ Oak Grove 230 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Westmoreland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Westmoreland _x0013_ Oak Grove 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.