PJM-AG2-477
0.5 MW generation in York, PA · In queue since March 2021 · Proposed COD April 2022
0.5 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 1m
Schedule
49 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-04-30
PJM-AG2-477 is a proposed solar generation project located in York County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 0.5 MW, consists of a single 0.5 MW solar component. The project's point of interconnection is the Hokes-Jackson 69 kV III substation.
The project entered the PJM interconnection queue on March 31, 2021, with a proposed commercial operation date of April 30, 2022. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Hokes-Jackson 69 kV III
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-477