Derry Tap-Derry Bus 69 kV III
20 MW generation in Northumberland, PA · In queue since February 2025
20 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Derry Tap-Derry Bus 69 kV III project is a proposed 20 MW solar generation project located in Northumberland County, Pennsylvania. The project is listed in the PJM interconnection queue as entry PJM-AG2-481, which was later moved to queue TC2. The queue entry date is February 3, 2025.
The project's status is listed as active. The interconnecting utility is PPL.
Generated from interconnection queue and public data sources
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Derry Tap-Derry Bus 69 kV III