PJM-AG2-492
50 MW storage in White, IN · In queue since March 2021 · Proposed COD September 2024
50 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 6m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed project PJM-AG2-492 is a 50 MW battery storage development in White County, Indiana. Interconnecting to the PJM grid at the Meadow Lake 345 kV point of interconnection, the project entered the queue on March 31, 2021, with a proposed commercial operation date of September 1, 2024. The interconnection agreement is currently listed as "In Progress (unknown study)".
The project, sponsored by AEP, consists solely of battery storage. It is currently listed as an active project within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Meadow Lake 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEADOWLK34.5 KV MEDWLKWF
- POI Substation
- Meadow Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-492