PJM-AG2-509
55 MW hybrid in WV · In queue since March 2021 · Proposed COD June 2024
55 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
PJM-AG2-509 is a proposed 55 MW hybrid solar and battery energy storage project located in West Virginia within the PJM Interconnection region. The project, consisting of 55 MW of solar generation, entered the PJM queue on March 31, 2021, with a proposed commercial operation date of June 1, 2024. The interconnecting utility is AEP, and the point of interconnection is the Robinson 69 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". There has been recent news coverage of the project.
Generated from interconnection queue and public data sources
State
WV
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Robinson 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-509