PJM-AG2-515
100 MW generation in Lucas, OH · In queue since March 2021 · Proposed COD October 2023
100 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 7m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AG2-515 is a proposed 100 MW solar generation project located in Lucas County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. The proposed commercial operation date is October 31, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is located within the service territory of utility ATSI. The point of interconnection is Midway 345 kV III.
Generated from interconnection queue and public data sources
State
OH
County
Lucas
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Midway 345 kV III
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Midway
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-515