PJM-AG2-516
120 MW generation in Winnebago, IL · In queue since March 2021 · Proposed COD October 2023
120 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 7m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AG2-516 is a proposed solar generation project located in Winnebago County, Illinois, within the PJM Interconnection region. The project, with a total capacity of 120 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is at the Pecatonica 138kV substation.
The project entered the PJM interconnection queue on March 31, 2021, with a proposed commercial operation date of October 31, 2023. As of the latest data, the project's interconnection agreement status is listed as "In Progress (unknown study)". The utility involved in the interconnection is ComEd.
Generated from interconnection queue and public data sources
State
IL
County
Winnebago
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Pecatonica 138kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-516