PJM-AG2-519
112 MW generation in Delaware, IN · In queue since March 2021 · Proposed COD February 2024
112 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-29
The proposed project PJM-AG2-519 is a 112 MW solar generation project located in Delaware County, Indiana. The project is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of February 29, 2024. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Royerton - Desoto 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-519