Five Forks DP - Littleton DP 115 kV
80 MW generation in Warren, NC · In queue since February 2025
80 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Five Forks DP - Littleton DP 115 kV project is a proposed 80 MW solar generation project located in Warren County, North Carolina. The project is being developed within the Dominion service territory and has appeared in recent news coverage. It is listed in the PJM interconnection queue as project PJM-AG2-522, which was subsequently moved to queue TC2. The queue entry date is February 13, 2025.
The project is currently listed as active in the PJM interconnection queue. It is seeking a Generation Interconnection service type.
Generated from interconnection queue and public data sources
State
NC
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Five Forks DP - Littleton DP 115 kV