Project PJM-AG2-524 — Project Summary

Queue ID
PJM-AG2-524
Capacity
110 MW
Technology
Solar+Battery
Status
active
Location
Grundy, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AG2-524

PJM-AG2-524BetaActiveSolarBatteryPJMLBNL

110 MW hybrid in Grundy, IL · In queue since March 2021 · Proposed COD December 2023

110 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

2y 9m

Schedule

28 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

About

PJM-AG2-524 is a proposed 110 MW hybrid solar and battery project located in Grundy County, Illinois. The project consists of 110 MW of solar generation. It is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021, with a proposed commercial operation date of December 31, 2023. The interconnection agreement is currently listed as "In Progress (unknown study)".

The proposed project is located within the ComEd utility service area and its point of interconnection is the LaSalle Station - Mazon 138 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Grundy

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

ComEd

Entity

PJM

Service Type

Point of Interconnection

LaSalle Station - Mazon 138 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
N ILLINOIS HUB
Hub Confidence
HIGH
POI Substation
Station 2

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.