PJM-AG2-527
200 MW generation in Stark, IL · In queue since March 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Wind
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AG2-527 is a proposed wind generation project with a total capacity of 200 MW. The project is located in Stark County, Illinois, within the ComEd service area and the PJM Interconnection region. The queue entry date is March 31, 2021, with a proposed commercial operation date of December 31, 2025.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Kewanee-Toulon 138 kV line. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Stark
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kewanee-Toulon 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.