PJM-AG2-532
20 MW storage in Warren, NJ · In queue since March 2021 · Proposed COD August 2022
20 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 5m
Schedule
45 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-08-31
PJM-AG2-532 is a proposed 20 MW battery storage project located in Warren County, New Jersey. The project is interconnected within the PJM Interconnection queue, with an entry date of March 31, 2021. The proposed commercial operation date is August 31, 2022.
The interconnection agreement status is listed as "In Progress (unknown study)". The designated utility is JCPL, and the point of interconnection is the Newburgh-Newburgh Tap 34.5 kV line.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Newburgh-Newburgh Tap 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.