PJM-AG2-538
20 MW hybrid in Elk, PA · In queue since March 2021 · Proposed COD October 2022
20 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 7m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-15
PJM-AG2-538 is a proposed 20 MW hybrid solar and battery project located in Elk County, Pennsylvania. The project, consisting of 20 MW of solar generation, is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of October 15, 2022. The interconnecting utility is APS.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Ridgeway - Motion Control 46 kV substation.
Generated from interconnection queue and public data sources
State
PA
County
Elk
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Ridgeway - Motion Control 46 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-538