PJM-AG2-541
65 MW hybrid in Halifax, VA · In queue since March 2021 · Proposed COD June 2024
65 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-03
PJM-AG2-541 is a proposed 65 MW hybrid solar and battery project located in Halifax County, Virginia. The project, which consists of 65 MW of solar capacity, is interconnected within the PJM Interconnection queue. Its queue entry date is March 31, 2021, with a proposed commercial operation date of June 3, 2024. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The project is within Dominion Energy's service territory. No developer is listed in the queue. The point of interconnection (POI) is the Perth - Crystal Hill 115 kV substation. The project has not appeared in recent news, nor is it linked to an existing operating plant in the EIA database.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Perth - Crystal Hill 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-541