PJM-AG2-542
70 MW hybrid in Rockingham, VA · In queue since March 2021 · Proposed COD June 2024
70 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-03
PJM-AG2-542 is a proposed 70 MW solar and battery hybrid project located in Rockingham County, Virginia. The project consists of 70 MW of solar generation. It is listed in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of June 3, 2024. The interconnection utility is Dominion.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the North Shenandoah _x0013_ Merck 115 kV line. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Rockingham
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
North Shenandoah _x0013_ Merck 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-542