PJM-AG2-550
100 MW generation in Randolph, IN · In queue since March 2021 · Proposed COD October 2024
100 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 7m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
The proposed project PJM-AG2-550 is a 100 MW solar generation project located in Randolph County, Indiana. Interconnecting to the AEP utility via the Bluff Point - Randolph 138 kV point of interconnection, the project entered the PJM interconnection queue on March 31, 2021, with a proposed commercial operation date of October 31, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 100 MW of solar photovoltaic generation capacity. It is currently listed as an active project within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Bluff Point - Randolph 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-550