PJM-AG2-551
50 MW storage in Randolph, IN · In queue since March 2021 · Proposed COD October 2024
50 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 7m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
PJM-AG2-551 is a proposed 50 MW battery storage project located in Randolph County, Indiana. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021, with a proposed commercial operation date of October 31, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project, which is being developed within the AEP utility territory, consists solely of battery storage with a total capacity of 50 MW. The point of interconnection is the Bluff Point - Randolph 138 kV line. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Bluff Point - Randolph 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-551