PJM-AG2-561
20 MW generation in Indiana, PA · In queue since March 2021 · Proposed COD December 2023
20 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-15
The proposed project PJM-AG2-561 is a 20 MW solar generation project located in Indiana County, Pennsylvania. It is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. The proposed commercial operation date is December 15, 2023. The project's interconnection agreement status is currently "In Progress" with an unknown study.
The project is located within the PENELEC utility territory. The point of interconnection is the Glory - Glen Campbell 34.5 kV line. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Glory - Glen Campbell 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- J H Campbell
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-561