PJM-AG2-564
49.99 MW generation in Crawford, OH · In queue since March 2021 · Proposed COD July 2024
49.99 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-01
The proposed project PJM-AG2-564 is a 49.99 MW solar generation project located in Crawford County, Ohio. It is interconnected within the PJM Interconnection queue, with a queue entry date of March 31, 2021, and a proposed commercial operation date of July 1, 2024. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Sulphur Springs 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.