Stink Run - Sundial 138 kV
80 MW generation in WV · In queue since February 2025
80 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Stink Run - Sundial 138 kV project is a proposed 80 MW solar generation project located in West Virginia. The project is listed in the PJM interconnection queue as entry PJM-AG2-568, though it has been moved to queue TC2. The queue entry date is February 21, 2025.
The project is currently listed as active in the queue. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
WV
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Stink Run - Sundial 138 kV