PJM-AG2-580
150 MW generation in Brunswick, VA · In queue since January 2021 · Proposed COD October 2024
150 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
PJM-AG2-580 is a proposed solar generation project with a total capacity of 150 MW, located in Brunswick County, Virginia. The project is being developed within the Dominion service area and has an interconnection queue entry date of January 29, 2021, in the PJM Interconnection queue. The proposed commercial operation date is October 1, 2024.
The interconnection agreement for PJM-AG2-580 is currently listed as "In Progress (unknown study)". The point of interconnection is the Rawlings-Clover 500 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Rawlings-Clover 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.