PJM-AG2-582
2,100 MW generation in Doddridge, WV · In queue since March 2021 · Proposed COD July 2026
2,100 MW
Capacity
1
Components
Gas
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
PJM-AG2-582 is a proposed 2100 MW gas-fired generation project located in Doddridge County, West Virginia. The project is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of July 1, 2026. The interconnecting utility is APS.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Belmont-Flint Run 500 kV line.
Generated from interconnection queue and public data sources
State
WV
County
Doddridge
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Belmont-Flint Run 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-582