PJM-AG2-583
115 MW generation in Cumberland, VA · In queue since March 2021 · Proposed COD June 2026
115 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
PJM-AG2-583 is a proposed solar generation project with a total capacity of 115 MW. The project is located in Cumberland County, Virginia, and is being developed within the Dominion service area. It entered the PJM interconnection queue on March 31, 2021, with a proposed commercial operation date of June 30, 2026.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Bremo - Cartersville 230 kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Bremo - Cartersville 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.