PJM-AG2-587
50 MW hybrid in Harford, MD · In queue since March 2021 · Proposed COD June 2024
50 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The proposed project PJM-AG2-587 is a 50 MW hybrid solar and battery energy storage project located in Harford County, Maryland. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. The proposed commercial operation date is June 1, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Graceton 230 kV substation. The distribution utility is BGE.
Generated from interconnection queue and public data sources
State
MD
County
Harford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
BGE
Entity
PJM
Service Type
—
Point of Interconnection
Graceton 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- Graceton Substation