PJM-AG2-600
19.6 MW generation in Warren, NJ · In queue since March 2021 · Proposed COD April 2021
19.6 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
1 month
Schedule
61 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-04-30
PJM-AG2-600 is a proposed solar generation project located in Warren County, New Jersey, within the PJM Interconnection region. The project, with a total capacity of 19.6 MW, consists entirely of solar photovoltaic generation. The interconnecting utility is Jersey Central Power & Light (JCPL).
The project entered the PJM interconnection queue on March 31, 2021, with a proposed commercial operation date of April 30, 2021. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the American Can-BASF 34.5 kV grid location.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
American Can-BASF 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM