PJM-AG2-603
150 MW hybrid in Carroll, VA · In queue since March 2021 · Proposed COD October 2024
150 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 7m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
PJM-AG2-603 is a proposed 150 MW hybrid Solar+Battery project located in Carroll County, Virginia. Interconnection is being managed through the PJM queue, with an entry date of March 31, 2021. The proposed commercial operation date is October 31, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 150 MW of solar generation capacity. The interconnection utility is AEP, and the point of interconnection is Huffman 138 kV. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Carroll
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Huffman 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HUFFMAN 138 KV T2
- POI Substation
- Huffman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-603