PJM-AG2-606
89 MW generation in Perry, PA · In queue since March 2021 · Proposed COD June 2024
89 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
PJM-AG2-606 is a proposed solar generation project with a total capacity of 89 MW, located in Perry County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. The proposed commercial operation date is June 1, 2024.
The interconnection agreement (IA) status for PJM-AG2-606 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Sunbury-Juniata 500 kV line. The utility involved is PPL.
Generated from interconnection queue and public data sources
State
PA
County
Perry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Sunbury-Juniata 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-606