PJM-AG2-618
110 MW generation in Charles, MD · In queue since March 2021 · Proposed COD December 2023
110 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG2-618 is a proposed 110 MW solar generation project located in Charles County, Maryland. The project is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of December 31, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Morgantown 230 kV substation, and the interconnecting utility is PEPCO.
The development project consists of 110 MW of solar photovoltaic generation. The project is listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
MD
County
Charles
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PEPCO
Entity
PJM
Service Type
—
Point of Interconnection
Morgantown 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MORGANTO13 KV CT3
- POI Substation
- Morgantown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-618