PJM-AG2-621
150 MW storage in Beaver, PA · In queue since March 2021 · Proposed COD May 2023
150 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 2m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-31
PJM-AG2-621 is a proposed 150 MW battery storage project located in Beaver County, Pennsylvania. The project is being developed within the PJM Interconnection queue, with an initial queue entry date of March 31, 2021. The proposed commercial operation date is May 31, 2023.
The interconnection agreement for PJM-AG2-621 is currently listed as "In Progress (unknown study)". The project is interconnected to the ATSI utility grid at the Hoytdale 138 kV point of interconnection.
Generated from interconnection queue and public data sources
State
PA
County
Beaver
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Hoytdale 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HOYTDAL2138 KV SVC
- POI Substation
- Hoytdale Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-621