Hoytdale 138 kV
150 MW storage in Beaver, PA · In queue since February 2025
150 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Hoytdale 138 kV project is a proposed 150 MW battery storage project located in Beaver County, Pennsylvania. The project is being developed within the PJM Interconnection queue under queue ID PJM-AG2-621, which was moved to TC2. The queue entry date is February 26, 2025.
The project's interconnection status is listed as active. The designated utility for interconnection is ATSI. The service type is Generation Interconnection.
Generated from interconnection queue and public data sources
State
PA
County
Beaver
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hoytdale 138 kV