PJM-AG2-626
12.5 MW generation in Warren, NJ · In queue since March 2021 · Proposed COD April 2021
12.5 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
1 month
Schedule
61 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-04-30
PJM-AG2-626 is a proposed solar generation project with a total capacity of 12.5 MW, located in Warren County, New Jersey. The project is in the PJM interconnection queue, having entered on March 31, 2021. The proposed commercial operation date is April 30, 2021. The project's interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is JCPL, and the point of interconnection is Pequest River-Furnace Brook Tap 34.5 kV III.
The development project consists of 12.5 MW of solar photovoltaic generation. The queue ID is PJM-AG2-626.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Pequest River-Furnace Brook Tap 34.5 kV III
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-626