PJM-AG2-627
40 MW generation in Gloucester, NJ · In queue since March 2021 · Proposed COD June 2024
40 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
The proposed project PJM-AG2-627 is a 40 MW solar generation project located in Gloucester County, New Jersey. The project is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of June 30, 2024. The interconnection agreement (IA) status is listed as "In Progress (unknown study)".
The project, which is being developed within the Atlantic Electric Company (AEC) service territory, consists of 40 MW of solar photovoltaic generation. The point of interconnection (POI) is the Woodstown-High Street 69 kV line. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
NJ
County
Gloucester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Woodstown-High Street 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-627