PJM-AG2-655
500 MW generation in Grant, WV · In queue since March 2021 · Proposed COD June 2024
500 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
PJM-AG2-655 is a proposed solar generation project with a total capacity of 500 MW, located in Grant County, West Virginia. The project is in the PJM interconnection queue as of March 31, 2021, with a proposed commercial operation date of June 30, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is being developed within the Dominion utility territory and interconnects at the Mt. Storm-Bismark 500 kV point of interconnection.
Generated from interconnection queue and public data sources
State
WV
County
Grant
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Mt. Storm-Bismark 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.